A FLOATING INFRASTRUCTURE CONCEPT
A power plant. A datacenter. One ship.
Follow the fuel, power, data and heat.
Explore what it takes to keep compute afloat.
MOORED · SHORE GASSCHEMATIC / NOT TO SCALE
Building the shipLoading the explorable model…
Drag to orbit · Scroll to zoom
CHANGE AN ASSUMPTION
Same ship. Different demands.
Screening estimates update as you explore.
10 MW80 MW
Datacenter supply demand
60.0 MW
PUE fixed at 1.20. Generator-side auxiliaries are included in net efficiency.
15°C40°C
Facility cooling margin POSITIVE
+5 °C
35°C estimated supply against an assumed 40°C ceiling.
$2/MMBtu$15/MMBtu HHV
Annual fuel cost FUEL ONLY
$29.9 million